Category Archives: Construction Update

House Completion

Well finally at the end of May we got our official completion certificate from the Council, which means we now officially have a house. The upside is that everything is now legal, including the swimming pool that we added.  The … Continue reading

Posted in 2017, Construction Update, House & Garden, Project Portugal | 1 Comment

July 2016

There is not a lot to say this month, I think I have said before the main project is now all but finished and we are in to general remarks about general things about running any house, which let’s be … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

June 2016

June has been a far better month, I know we were late posting May’s blog, but that was more because we had some issues as I am sure you have read and we wanted to at least get some of … Continue reading

Posted in 2016, Casa Neroli - Photos, Construction Update, General, Project Portugal | 1 Comment

May 2016

Disaster Strikes Well that may be a little over dramatic but it got your attention. The start of May proved to be the wettest period recorded since records began for Portugal. The persistent heavy rain at the start of the … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

April 2016

Despite the very changeable weather this month we have managed to progress work on the farm and garden areas.     The beginning of the month was really quite wet so it was difficult for the workmen to get on … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | 4 Comments

March 2016

It was a wet start to the month so the work on the agricultural element of the project was delayed yet again. However, around the middle of the month the weather improved enough that the work could really get under … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

February 2016

So February has seen the gates all installed, although we are going to have to get the paver back at some point to adjust and tidy up the granite blocks on the drive as the locksmith had to lower some … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

January 2016

January has been a bad month weather wise in Portugal, although you wouldn’t think so looking at this picture. Taken on one of the good days. The consequence has been that the land around our property has been very wet … Continue reading

Posted in 2016, Construction Update, Project Portugal | Leave a comment

December 2015 – Update

Well here we are at the end of the year. Today is the first day of 2016 and we are enjoying a peaceful first day of the new year in Casa Neroli. It is somewhat wet and very misty outside … Continue reading

Posted in 2015, Construction Update, General, Project Portugal | Leave a comment

November 2015 – Update

November has been a very quiet month in terms of actual work being completed. Not surprising really as the main build is complete and we are now into getting the garden and farm organised. Our plan is to make both … Continue reading

Posted in 2015, Construction Update, General, Project Portugal | Leave a comment