Category Archives: 2016

The Old Hut – The story so far

At the start of the building of the house project, we needed to get electricity on the site. The main supply, delivered by overhead cables was already to the edge of the plot so we just had to drop a … Continue reading

Posted in 2016, Project Portugal, The Hut | Leave a comment

The Old Hut

The original hut that came with the land when we brought it is just in the way of the view towards Monsanto, so it has to go. It’s been great having it whilst we have been building the house, somewhere … Continue reading

Posted in 2016, Project Portugal, The Hut | Leave a comment

Tractor

Yes, we have made the decision that we need to get a small tractor!!! Whilst it has been fun and somewhat fulfilling strimming the land each time we visit, now the house is there we want to enjoy that more, … Continue reading

Posted in 2016, Project Portugal, Tractor | Leave a comment

The Farm

Background The original farm was about 2 acres, we have used about half of that to place the house and pool and have added about another acre with an addition purchase, so are back to about 2 acres. The newer … Continue reading

Posted in 2016, Project Portugal, The Farm | Leave a comment

July 2016

There is not a lot to say this month, I think I have said before the main project is now all but finished and we are in to general remarks about general things about running any house, which let’s be … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

June 2016

June has been a far better month, I know we were late posting May’s blog, but that was more because we had some issues as I am sure you have read and we wanted to at least get some of … Continue reading

Posted in 2016, Casa Neroli - Photos, Construction Update, General, Project Portugal | 1 Comment

May 2016

Disaster Strikes Well that may be a little over dramatic but it got your attention. The start of May proved to be the wettest period recorded since records began for Portugal. The persistent heavy rain at the start of the … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

April 2016

Despite the very changeable weather this month we have managed to progress work on the farm and garden areas.     The beginning of the month was really quite wet so it was difficult for the workmen to get on … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | 4 Comments

March 2016

It was a wet start to the month so the work on the agricultural element of the project was delayed yet again. However, around the middle of the month the weather improved enough that the work could really get under … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment

February 2016

So February has seen the gates all installed, although we are going to have to get the paver back at some point to adjust and tidy up the granite blocks on the drive as the locksmith had to lower some … Continue reading

Posted in 2016, Construction Update, General, Project Portugal | Leave a comment